Client:
Western Communications, Inc.
Architect: Dario Designs, Inc.
Construction Costs: $7,788,950
Completion Date: September 2000
Contract Type: Guaranteed Maximum
Price (GMP)
Scope
of Work: The new production facility for the Bulletin newspaper
plant consists of an 86,470 SF two-story, steel framed, block veneer
building, complete with all mechanical & electrical systems, and
complete site development and landscaping. The production facility includes
not only office area for newspaper staff and photo department, but also
a specialized, state-of-the-art printing press room, newspaper storage,
shipping and receiving and mailing facilities.